Building the Hayes Knoll Restoration Shed Extension
|
||||
![]() |
Initially we had to clear the site and move a large
amount of rubbish and scrap which had accumulated including large piles
of wood, and even an old rusty lathe which weighed a few tonnes.
|
|||
|
|
Everything seemed very heavy to move and this job took
several weeks. In addition we faced a problem in that a large water
tank from a 10 tonne milk wagon was buried beneath the site. The drain
pipes from the roof of the building feed rain water into the tank
which is then pumped out using a diesel pump and used to water the
locos. We obtained a large steel girder that was lying
as scrap in the Swindon Cricklade's Blunsdon car park. Will the help
of some of the other Swindon Cricklade members this was moved using
the hiab-crane and a diesel shunter to the site. Originally the girder
came from Swindon works and it has a what I think is broad gauge rail
welded to it and was used as the rail support for one of the travelling
cranes in the works, so it's a genuine piece of GWR steel !! The four foundations holes were dug by hand, and were roughly a metre deep by a metre square. They were dug in winter and as the ground is clay they kept filling with water. In the middle of winter with frost on the ground you do question your own sanity and it made the ground harder for digging. The next step was the concreting which was completed with the help of some of the volunteers at the SCR. As there is no road access to Hayes Knoll (its in the middle of a field), all the ready mixed concrete had to be loaded into builders merchant bags at Blunsdon and then each one lifted into an open rail wagon using the hiab-crane belonging to the SCR. The wagon and concrete was then shunted half a mile to Hayes Knoll and then the bags one by one lifted using the hiab crane over the areas which needed to be concreted. The concrete being deposited by splitting the bags with a Stanley knife. We also did the concreting for the pathways at the same time and this is still not quite complete. This process involved many people and it was made difficult because of the lack of road access. Once all the concreting had been completed we
were able to get the contractors in to put up the steel framework,
cladding and roof. This was completed by them working just on Saturdays
as they needed the hi ab crane to be driven by one of the SCR volunteers.
This meant the process was very slow and in addition all materials
for the building needed to be brought down by train including the
contractor's ladders etc. This caused the contractors to keep delaying
the job as they didn't like the inconvenience of working at the site.
The building has a steel frame bolted together. The roof is made of
cement corrugated panels, with several clear plastic roof panels to
provide extra light. We got the contractors to come back and build
a new door frame for the end doors. The new hinges were added to the new end of the building and the doors (which are too heavy to be moved by hand) were lifted off the hinges with a bottle jack and moved to the new end of the building with the hiab crane (For pictures of this crane in use see the SCR website) The final stage was to demolish the original door frame on the existing building, and then shunt the coach inside.