We have been busy on the
project on Wednesdays, Saturdays and Sundays and have passed the milestone
of having the frame repairs complete and by Christmas 06 the whole
outside of the coach (with the exception of the doors) was re panelled.
This is a major step forward and the coach no longer looks the "no-hoper"
it did at the start.
This is very satisfying
especially as in 2007 the coach will be 100 years old (being completed
on 14th December 1907). Originally it cost £1268-12s- 1d to
build ! Having been inspired by the recent Woodbine "birthday
party" we thought we might use a similar excuse to drink beer
etc and have our own 100 candle event. ! so in the summer we would
like to get the coach pushed outside and on display for a day or two,
ideally in the bay platform at Hayes Knoll so the public can come
and take a look inside, we still need to discuss with management and
decide on a weekend probably in August and ideally tying up with a
larger event at the SCR. The major focus for 2007 will be the 16 external
doors, 5 of these have been done already (but not all re hung) and
we intend to have all the external doors complete and re fitted to
the coach by the end of 2007.
The first set Ken Habgood
will work on is the guards doors, these are a double set so are a
bit more complicated to do.
Andrew Creaser has completed a whole set of the ventilator boxes that
are attached to the inside of each door at the top.
Ken recently has been working on making new framing for the floor
in the guards compartment which is being done different to the original
way and is being re-laid with 2 layers of 15mm Russian birch ply.We
have also been getting companies to cast other parts for the doors
and make rubber bumpers etc.The group had another trip to the Severn
Valley Railway to meet Colin Jenkins and it was a good opportunity
for newer members of the group such as Tony Davis and Alan Merryweather
to see the three restored and one un restored Toplights at the SVR.
The un restored one the
SVR plan to start work on in the not too distant future. They have
been collecting bits for it, but currently are working on a Gresley
vehicle and another 1930s GWR coach, both of which are probably about
80% done.The Severn Valley ones have been modified in a number of
ways:-1 They have been fitted with dump valves so that if the Guard
screws the handbrake on, then this means that the vacuum cannot be
created to lift the main brakes off.
If the guard forgets to
screw the hand brake to off it prevents the coach being dragged along
with the handbrake screwed on and the wheels locked, thus causing
a wheel flat, which is both expensive and very, very difficult with
limited tools and no jacks to correct. (we have no spare bogies which
we can just swap etc).
We may already have wheel
flats, we don't know yet, but it seems unlikely as the tyres themselves
are quite thick and in good condition.This seems like a good modification
to fit so we will make sure we make the same modification, although
on the SCR it should be generally less of a problem as we tend to
use small locomotives which don't have as much "pull" so
it would be more obvious to the driver that something was wrong if
the coach handbrake is left on. 2 They have added pipes underneath
the coach so both toilet tanks can be filled from ground level by
connecting up a hose pipe. The pipes themselves run through to near
the centre of the chassis with a Tee piece so that there is a nozzle
at either side.
The reason for do this
is that the SVR found that if the pipes come down at the end then
the bogie will damage them when the coach goes round a bend. The SVR
found this by trial and error when heads were scratched upon seeing
some mangled water pipe !!
Originally the tanks where filled from the roof lid, but this means
someone has to climb on the roof each time. We may decide to fit this
but perhaps not straight away, as it is doubtful the toilets will
be used whilst we are only running such a short distance but other
railways such as the Gloucester Warwickshire and SVR do use them.3
The one which was originally mahogany panelled was at first restored
with plywood but then later rebuilt with steel as they found after
6 to 7 years open storage that the coach was unusable (they are stored
undercover now).One of the reasons we went to the Severn Valley was
to look at the lighting system so this will now be described in some
detail:-Originally when 7545 was built in 1907 for newly constructed
coaches there were basically two main lighting systems in use in Britain,
Gas or Electric.
Gas was the older and by
that time Compressed Oil gas was the normal method, this had been
introduced on the Metropolitan Railway in 1876. Oil gas was made in
a separate gas plant by means of distillation, and the railways generally
built their own gasworks for the purpose (there was one in Swindon
for instance). The coaches themselves would then be filled either
directly from a supply or from a gas wagon which carried gas for this
purpose to more remote areas.Underneath the coach there would have
been gas cylinders typically about 6 feet long and about 1.75 feet
in diameter and unusually pressured to about 80 -100 PSI. There would
have then been a pressure gauge on each side of the chassis and you
can still see today where the mounting holes for these were, as well
as the mountings for the gas tanks themselves (they have been riveted
to fill the holes.)From the gas tanks there would then have been small
copper piping along the top of the roof and into each of the gas lights.
These went right through the roof so that the "chimney"
could vent through the roof. A regulating valve kept the supply pressure
constant and a pullout handle meant that staff could switch all the
lamps on or off simultaneously. (each lamp had a small pilot light).
Both the GWR and Midland
stuck to gas lighting well after other railways had moved to Electricity
and were both typically slow to adopt new ideas. We did consider the
possibility of reinstalling the gas system. There is a GWR 1897 sleeping
car on the West Somerset Railway that has recently been fully restored(Some
of you may have seen it at the Spring gala on that line with its gas
lights on). It looks like a Toplight but has a Clerestory roof and
has beds in it. This has been restored with working gas lights and
cooker so I contacted them to find out what was involved.
The HMRI had not really
liked it but had agreed to approve it and it had been installed by
a CORGI registered volunteer.
They had to fit a special tumbler valve so that if the coach turns
over !! then the gas supply is automatically switched off. They used
two propane tanks holders off an old Camping coach. The original gas
lights were made by a company called William Sugg who were at the
time a major supply of gas lights all over the world, they mostly
made street lighting and also the gas lights you typically see on
station building/platforms/canopies as well as approx 15000 hand oil
lamps for the GWRs drivers, guards etc.Amazingly enough they still
exist and make many of the same range using some original tools etc
and run by a descendant of the founder and you can see their range
at
www.sugglighting.co.uk if you fancy some Victorian lamps in your garden
!
They have many different
types both gas and electric and would look nice on our station platform.
The gas ones are switched on electrically by an electric solenoid
just opening a gas valve and with a pilot light the gas ignites automatically.
If we do build a "period" station at Cricklade they would
look great.So anyway Suggs specially made a new set of 10 lamps for
the West Somerset Sleeping car, however (and here is the snag !) they
cost £7000 for the patterns to original drawings (Swindon historic
Castings had some of the main patterns) and then a further £7000
for the lamps to actually be made, plus money to convert the cooker
to propane gas. Full credit for the WSR to going to this trouble with
the detail, and for those that have seen it the whole project has
been done to "museum quality" standards.Now to the electrical
system, if you haven't fallen asleep already.
7545 was converted from
gas to electric in the 1930s and all the original gas fittings were
removed. The electrical system was basically the same on all GWR coaches
right from the 1920s until the GWR coaches were withdrawn without
much variation from what I can see.
The main parts were as
follows:-
1 The dynamo
2 The batteries (12 lead acid cells)
3 The Auto Switch
4 The Distance Switch
5 The regulator
6 The though train control switch
We have now acquired the
bits we need for the system. The dynamo is driven by pulleys and a
belt from one of the main wheels, its designed so that it has a mechanism
so that it still provides the same voltage polarity regardless of
which direction the coach is travelling, ( i.e. it can rotate clock
or anticlockwise)The auto switch controls whether current is coming
from either the batteries or the dynamo, by measuring the voltage
of the dynamo.
The distance switch is
used to switch the lights on or off in the coach and is located in
the guards compartment, together with the through train control switch
which can switch lights on or off in the whole train.
The final part the regulator
is very heavy and complicated, it would take me several pages to explain
how it works properly so simply, it keeps the lights on the train
at a constant voltage (and therefore brightness) regardless of how
many lights are on or off in each compartment by adjusting the amount
of resistance in the 3 individual circuits depending on the number
of lights that are on.
Alan Merryweather has been
busy on a number of items cleaning metals parts and then painting
them. He has been coming regularly and is getting more experienced
at doing the work needed, so has become a very useful member of the
team. Alan has also been doing repairs to some of our equipment such
as steps, wood vices etc.Tony Davis has been working on all the door
hinges carefully removing them from the body and then taking the pins
out and cleaning them up before putting them back on the body. When
the doors are refitted the holes are plugged, re-drilled and then
new screws put in, this ensures that the doors are fitted on strongly.Finally
as the coach is getting more complete and there are less and less
rotten areas so it's getting more satisfying to work on.





New Floor in guards compartment